Facilities Guideline Plan for the 21st
Century
November 20, 1998
|
|
|
|
Project Phasing
and Sequencing
Potential project
phasing is illustrated below. Project sizes and phasing are subject
to revisions as planning proceeds. Cost estimates are for total project
costs, including construction, design fees, permits fees, and other
"soft" costs. The estimates are shown in 1998 dollars and
must be adjusted to reflect changes in cost between 1998 and the year
each project is constructed.
|
PHASE
I
|
|
Project
|
Project
Specifications
|
Cost
Estimate
(1998
Dollars)
|
- Construct
Emerson Street Residential Facility w/Parking Garage
Pre-construction
- Renovate
SPU-owned house within the boundary for Human Resources
- Relocate
Human Resources
- Demolish
houses on Emerson Street site
Post-construction
- Eliminate
Marston and perhaps Watson from student housing inventory
- Demolish
structures
- Create
expanded surface parking
|
Building
86,000 SF
Beds
290320
Garage 44,000
SF,
140
stalls
Surface
Lot 50 stalls
|
Project
Cost
$14,007,000
Additional
Costs:
$65,000
$4,500
$71,000
$0
$65,000
$200,000
|
|
Project
|
Project
Specifications
|
Cost
Estimate
(1998
Dollars)
|
- Construct
Phase I Science Facility w/Classroom(s)
Pre-construction
- Renovate
Marston and perhaps Watson to accommodate functions
in Tiffany and Green
- Relocate
School of Health Sciences to Marston
- Relocate
all occupants of Tiffany (Security, IKON, faculty offices,
etc.) to Marston/Watson
- Demolish
Tiffany and Green
Post-construction
- Relocate
designated science programs and faculty offices to
new science facility
- Renovate
MSLC
|
48,545 SF
23,090 SF
52,611 SF
|
Project
Cost
$19,578,000
Additional Costs
$2,249,000
$22,413
$48,138
Included
in project cost
$78,916
$2,000,000
|
|
Project
|
Project
Specifications
|
Cost
Estimate
(1998
Dollars)
|
- Construct
Auditorium/Chapel w/Parking and University Piazza Entrance
Pre-construction
- Renovate
SPU-owned house within boundary for Division of Continuing
Studies
- Relocate
DCS from Rand Building
- Demolish
surface parking lot, Rand Building, and adjacent small
buildings
- Construct
Nickerson Street Parking Garage/Mixed Use Building
for use by SPU bookstore, offices and retail space
for bank, hair salon, dry cleaners, etc.
- Relocate
styling salon and dry cleaners
- Relocate
bookstore
- Relocate
bank
- Demolish
bookstore, bank and adjacent small buildings and create
surface parking
- Demolish
styling salon/dry cleaners building and create surface
parking
|
Building
40,000 SF
Piazza 10,000
SF
Parking
50 stalls
Parking
267 stalls
Mixed Use
19,000 SF
|
Project
Cost
$17,678,000
Additional Costs
$65,000
$8,839
$137,000
$6,981,000
$5,520
$15,384
$20,000
$63,000
$85,000
|
|
Project
|
Project
Specifications
|
Cost
Estimate
(1998
Dollars)
|
- Construct
Fine Arts Building w/Recital Hall and Classroom(s)
Pre-construction
- Demolish
Crawford Parking Lots
Post-construction
- Upgrade
Crawford Music Building
- Relocate
occupants of Beegle to new Fine Arts Facility
- Demolish
Beegle and create surface parking lot
- Relocate
programs and faculty offices from Art Center to new
facility
- Assign
old Art Center to Facility Management
|
33,000 SF
|
Project
Cost
$9,994,000
Additional Costs
$72,000
$1,192,000
$39,993
$130,000
$31,116
$0
|
|
PHASE
II
|
|
Project
|
Project
Specifications
|
Cost
Estimate
(1998
Dollars)
|
- Construct
Irondale Residential Facility w/Parking and Outdoor
Recreation Space
Pre-construction
- Demolish
houses on Irondale site (excluding 657 W. Bertona)
|
Building
34,000 SF
Beds
- 144
Garage
180 stalls
Surface
75 stalls
|
Project
Cost $10,210,000
Additional Costs
$60,000
|
|
Project
|
Project
Specifications
|
Cost
Estimate
(1998
Dollars)
|
- Construct
Professional Schools Building w/Classroom(s)
Pre-construction
- Demolish
parking lot on site
Post-construction
- Renovate
McKenna Hall and upgrade for seismic requirements
- Relocate
School of Health Sciences from Marston to Professional
Schools Building
- Relocate
MFT Program and Counseling/Health Center from Watson
to Professional Schools Building
- Relocate
Division of Continuing Studies from house and Demaray
to Professional Schools Building
|
42,000 SF
|
Project
Cost
$10,017,000
Additional Costs
$26,000
$3,017,000
$22,413
$31,410
$13,389
|
|
- Construct
Ashton Residential Complex & Additional Parking
Pre-construction
- Demolish
duplexes
|
Building
35,000 SF
Beds
- 120
Parking
93 stalls
|
Project
Cost
$7,024,000
Additional Costs
$18,000
|
|
Project
|
Project
Specifications
|
Cost
Estimate
(1998
Dollars)
|
- Construct
Phase II Science Building w/Classroom(s) and Space
for C.I.S.
Pre-construction
- Relocate
remaining occupants of Watson to Marston
- Demolish
Watson
Post-construction
- Relocate
remainder of science programs and faculty offices from
MSLC to new science facility
- Relocate
Computer & Information Systems from Marston to
new science facility
|
58,576 SF
|
Project
Cost
$20,103,000
Additional
Costs
$15,705
$82,000
$78,916
$41,000
|
|
Project
|
Project
Specifications
|
Cost
Estimate
(1998
Dollars)
|
- Renovate/Add
to Weter to Create the Student Center
Pre-construction
- Prepare
MSLC to accommodate functions currently in Weter
- Relocate
all functions from Weter to MSLC
Post-construction
- Relocate
functions in Student Union Building to Weter Student
Center
- Relocate
copy center from Marston to Weter Student Center
- Relocate
arcade games/pool table, etc. from MSLC to Weter Student
Center
|
19,208 SF
- existing
20,000 SF
- new
|
Project
Cost
$9,861,000
Additional
Costs
$1,587,000
$57,624
$60,867
$9,000
$15,000
|
- Renovate/Replace
Student Union Building to Create the University Center
w/Classroom(s) and Visitor Center
Post-construction
- Relocate
Development, Planned Giving, and University Communications
from MSLC to the University Center
- Relocate
Student Academic Services and Student Financial Services
from Demaray to the University Center
- Temporarily
relocate executive administrative offices from Demaray
into University Center
|
44,000 SF
|
Project
Cost
$11,096,000
Additional
Costs
$19,209
$46,359
$23,100
|
|
Project
|
Project
Specifications
|
Cost
Estimate
(1998
Dollars)
|
- Renovate
Portions of Demaray Hall for Faculty Offices and Classrooms
Post-construction
- Relocate
faculty offices from Marston to Demaray
- Relocate
faculty offices from Alexander to Demaray
|
27,000 SF
|
Project
Cost
$4,706,000
Additional
Costs
$24,069
$33,360
|
|
Project
|
Project
Specifications
|
Cost
Estimate
(1998
Dollars)
|
- Renovate
Alexander Hall for Executive Administration
Post-construction
- Relocate
executive offices from University Center to Alexander
Hall
- Relocate
Human Resources to the University Center
- Relocate
the Alumni Center to the University Center
- Relocate
Finance/Controllers Office and Seattle Pacific Foundation
from MSLC to the University Center
- Relocate
Security from Marston to University Center
|
8,900 SF
|
Project
Cost
$1,837,000
Additional
Costs
$23,100
$4,500
$3,840
$19,209
$6,000
|
- Renovate
MSLC for PE/Athletics/Recreation Space and Archives/Storage
Pre-construction
- Demolish
Alumni Center and adjacent houses to create temporary
surface parking lot
Post-construction
- Relocate
archives and storage from Stearns Building and other
various locations
|
52,611 SF
Parking
38 stalls
|
Project
Cost
$8,036,000
Additional
Costs
$59,000
$24,000
|
|
PHASE
III
|
|
Project
|
Project
Specifications
|
Cost
Estimate
(1998
Dollars)
|
- Construct
Plaza Classroom Facility
Pre-construction
- Demolish
Marston
|
20,000 SF
|
Project
Cost
$6,503,000
Additional
Costs
$179,000
|
|
Project
|
Project
Specifications
|
Cost
Estimate
(1998
Dollars)
|
- Construct
Parking Garage at Third & Dravus
Pre-construction
- Demolish
surface parking on site
|
Parking
- 264 stalls
|
Project
Cost
$5,470,000
Additional
Costs
$65,000
|
- Construct
Recreation Field
Pre-construction
- Demolish
surface parking and structures on site
- Remove
gas station equipment
|
Field 146,000
SF
|
Project
Cost
$1,900,000
Additional
Costs
$232,000
$33,000
|
|
Construct
Swimming Pool
Pre-construction
a. Demolish
surface parking on site
|
22,500 SF
|
Project
Cost
$5,643,000
Additional
Costs
$39,000
|
|
Bertona
Street/Emerson Street/Sixth Avenue Improvements *
Pre-construction
- Obtain
City approval of Bertona/Emerson/Sixth Avenue street
modifications or "greenstreets" designation
Post-construction
- Develop
transit mall at Third/Nickerson/Bertona
* Does
not include cost of necessary land acquisition
|
85,000 SF
24,000 SF
|
Project
Cost *
$1,887,000
$386,000
|
|