Facilities Guideline Plan for the 21st Century
November 20, 1998

Project Phasing and Sequencing

Potential project phasing is illustrated below. Project sizes and phasing are subject to revisions as planning proceeds. Cost estimates are for total project costs, including construction, design fees, permits fees, and other "soft" costs. The estimates are shown in 1998 dollars and must be adjusted to reflect changes in cost between 1998 and the year each project is constructed.

 
PHASE I
Project

Project Specifications

Cost Estimate

(1998 Dollars)

  1. Construct Emerson Street Residential Facility w/Parking Garage

    Pre-construction
  1. Renovate SPU-owned house within the boundary for Human Resources
  2. Relocate Human Resources
  3. Demolish houses on Emerson Street site

Post-construction

  1. Eliminate Marston and perhaps Watson from student housing inventory
  2. Demolish structures
  3. Create expanded surface parking

Building – 86,000 SF

Beds – 290–320

 

Garage – 44,000 SF,

140 stalls

Surface Lot – 50 stalls

Project Cost
$14,007,000

Additional Costs:
$65,000

$4,500

$71,000

$0

$65,000

$200,000

 
Project

Project Specifications

Cost Estimate

(1998 Dollars)

  1. Construct Phase I Science Facility w/Classroom(s)

Pre-construction

  1. Renovate Marston and perhaps Watson to accommodate functions in Tiffany and Green
  2. Relocate School of Health Sciences to Marston
  3. Relocate all occupants of Tiffany (Security, IKON, faculty offices, etc.) to Marston/Watson
  4. Demolish Tiffany and Green

Post-construction

  1. Relocate designated science programs and faculty offices to new science facility
  2. Renovate MSLC

48,545 SF

23,090 SF

 

 

 

 

 

 

52,611 SF

Project Cost

$19,578,000


Additional Costs

$2,249,000

$22,413

$48,138

Included in project cost

$78,916

$2,000,000

Project

Project Specifications

Cost Estimate

(1998 Dollars)

  1. Construct Auditorium/Chapel w/Parking and University Piazza Entrance

Pre-construction

  1. Renovate SPU-owned house within boundary for Division of Continuing Studies
  2. Relocate DCS from Rand Building
  3. Demolish surface parking lot, Rand Building, and adjacent small buildings
  4. Construct Nickerson Street Parking Garage/Mixed Use Building for use by SPU bookstore, offices and retail space for bank, hair salon, dry cleaners, etc.
  5. Relocate styling salon and dry cleaners
  6. Relocate bookstore
  7. Relocate bank
  8. Demolish bookstore, bank and adjacent small buildings and create surface parking
  9. Demolish styling salon/dry cleaners building and create surface parking

Building – 40,000 SF

Piazza – 10,000 SF

Parking – 50 stalls

 

 

 

Parking – 267 stalls

Mixed Use – 19,000 SF

Project Cost

$17,678,000


Additional Costs

$65,000

$8,839

$137,000

$6,981,000

$5,520

$15,384

$20,000

$63,000

$85,000

Project

Project Specifications

Cost Estimate

(1998 Dollars)

  1. Construct Fine Arts Building w/Recital Hall and Classroom(s)

Pre-construction

  1. Demolish Crawford Parking Lots

Post-construction

  1. Upgrade Crawford Music Building
  2. Relocate occupants of Beegle to new Fine Arts Facility
  3. Demolish Beegle and create surface parking lot
  4. Relocate programs and faculty offices from Art Center to new facility
  5. Assign old Art Center to Facility Management

33,000 SF

Project Cost $9,994,000


Additional Costs

$72,000

 

$1,192,000

$39,993

$130,000

$31,116

$0

 
PHASE II
Project

Project Specifications

Cost Estimate

(1998 Dollars)

  1. Construct Irondale Residential Facility w/Parking and Outdoor Recreation Space

Pre-construction

  1. Demolish houses on Irondale site (excluding 657 W. Bertona)

Building – 34,000 SF

Beds - 144

Garage – 180 stalls

Surface – 75 stalls

Project Cost $10,210,000

Additional Costs

$60,000

 

 
Project

Project Specifications

Cost Estimate

(1998 Dollars)

  1. Construct Professional Schools Building w/Classroom(s)

Pre-construction

  1. Demolish parking lot on site

Post-construction

  1. Renovate McKenna Hall and upgrade for seismic requirements
  2. Relocate School of Health Sciences from Marston to Professional Schools Building
  3. Relocate MFT Program and Counseling/Health Center from Watson to Professional Schools Building
  4. Relocate Division of Continuing Studies from house and Demaray to Professional Schools Building

 

42,000 SF

Project Cost
$10,017,000


Additional Costs

$26,000

 

$3,017,000

$22,413

 

$31,410

 

$13,389

 

  1. Construct Ashton Residential Complex & Additional Parking

Pre-construction

  1. Demolish duplexes

Building – 35,000 SF

Beds - 120

Parking – 93 stalls

Project Cost

$7,024,000


Additional Costs

$18,000

Project

Project Specifications

Cost Estimate

(1998 Dollars)

  1. Construct Phase II Science Building w/Classroom(s) and Space for C.I.S.

Pre-construction

  1. Relocate remaining occupants of Watson to Marston
  2. Demolish Watson

Post-construction

  1. Relocate remainder of science programs and faculty offices from MSLC to new science facility
  2. Relocate Computer & Information Systems from Marston to new science facility

58,576 SF

Project Cost

$20,103,000

Additional Costs

$15,705

$82,000

 

$78,916

$41,000

Project

Project Specifications

Cost Estimate

(1998 Dollars)

  1. Renovate/Add to Weter to Create the Student Center

Pre-construction

  1. Prepare MSLC to accommodate functions currently in Weter
  2. Relocate all functions from Weter to MSLC

Post-construction

  1. Relocate functions in Student Union Building to Weter Student Center
  2. Relocate copy center from Marston to Weter Student Center
  3. Relocate arcade games/pool table, etc. from MSLC to Weter Student Center

 

19,208 SF - existing

20,000 SF - new

Project Cost
$9,861,000

Additional Costs

$1,587,000

$57,624

 

$60,867

$9,000

$15,000

  1. Renovate/Replace Student Union Building to Create the University Center w/Classroom(s) and Visitor Center

Post-construction

  1. Relocate Development, Planned Giving, and University Communications from MSLC to the University Center
  2. Relocate Student Academic Services and Student Financial Services from Demaray to the University Center
  3. Temporarily relocate executive administrative offices from Demaray into University Center

44,000 SF

Project Cost

$11,096,000

Additional Costs

$19,209

$46,359

$23,100

Project

Project Specifications

Cost Estimate

(1998 Dollars)

  1. Renovate Portions of Demaray Hall for Faculty Offices and Classrooms

Post-construction

  1. Relocate faculty offices from Marston to Demaray
  2. Relocate faculty offices from Alexander to Demaray

27,000 SF

Project Cost

$4,706,000

Additional Costs
$24,069

$33,360

 
Project

Project Specifications

Cost Estimate

(1998 Dollars)

  1. Renovate Alexander Hall for Executive Administration

Post-construction

  1. Relocate executive offices from University Center to Alexander Hall
  2. Relocate Human Resources to the University Center
  3. Relocate the Alumni Center to the University Center
  4. Relocate Finance/Controller’s Office and Seattle Pacific Foundation from MSLC to the University Center
  5. Relocate Security from Marston to University Center

 

8,900 SF

Project Cost

$1,837,000

Additional Costs

$23,100

$4,500

$3,840

$19,209

$6,000

  1. Renovate MSLC for PE/Athletics/Recreation Space and Archives/Storage

Pre-construction

  1. Demolish Alumni Center and adjacent houses to create temporary surface parking lot

Post-construction

  1. Relocate archives and storage from Stearns Building and other various locations

52,611 SF

 

Parking – 38 stalls

Project Cost

$8,036,000

Additional Costs

$59,000

 

$24,000

 
PHASE III
Project

Project Specifications

Cost Estimate

(1998 Dollars)

  1. Construct Plaza Classroom Facility

Pre-construction

  1. Demolish Marston

20,000 SF

Project Cost

$6,503,000

Additional Costs

$179,000

 
Project

Project Specifications

Cost Estimate

(1998 Dollars)

  1. Construct Parking Garage at Third & Dravus

Pre-construction

  1. Demolish surface parking on site

 

Parking - 264 stalls

Project Cost

$5,470,000

Additional Costs

$65,000

  1. Construct Recreation Field

Pre-construction

  1. Demolish surface parking and structures on site
  2. Remove gas station equipment

 

Field – 146,000 SF

Project Cost

$1,900,000

Additional Costs

$232,000

$33,000

  • Construct Swimming Pool
  • Pre-construction

    a. Demolish surface parking on site

     

    22,500 SF

    Project Cost

    $5,643,000

    Additional Costs

    $39,000

  • Bertona Street/Emerson Street/Sixth Avenue Improvements *
  • Pre-construction

    1. Obtain City approval of Bertona/Emerson/Sixth Avenue street modifications or "greenstreets" designation

    Post-construction

    1. Develop transit mall at Third/Nickerson/Bertona

    * Does not include cost of necessary land acquisition

    85,000 SF

     

     

     

     

    24,000 SF

    Project Cost *

    $1,887,000

     

     

     

    $386,000


    Copyright © 1999 Seattle Pacific University.
    General Information: (206) 281-2000