Point of Contact: Janet Ward
CSOT Department/Area: CSOT Leadership / Primary Facilitator
To: Dave Church / FPM
Thanks Dave -- a follow up question.
We all know that plans and priorities can shift depending on the situation and updated direction from ECMT or President. When we look at the building prioritization, could you clarify where Marston (CIS) falls in relation to the Science Building, as I understand the Science building has a back-up server for CIS. There may be other issues tied to both buildings that need to be part of the decision (e.g. chemicals, etc.) – so wondering if the Science building because it is newer, is more likely to get clearance (and with a back-up server operating) may help us get computer systems up and running.
Thanks for sharing your insights.
--Janet
Janet Ward
Associate Vice President, Information and Data Management
(206) 281-2701
jward@spu.edu
www.spu.edu/depts/idm