Projects in Construction

Ashton and Hill Hall Telecommunications Upgrade

Project Manager: Wayne Elling, 206-281-2599, welling@spu.edu
Construction Timeline: June 12, 2007 - August 30, 2007
Engineer: Sparling Engineering
Contractor: Kirtley-Cole
SPU Ashton-Hill Schedule
Mon 6/11/07 Thu 9/6/07
Ashton Hall
Mon 6/11/07 Thu 9/6/07
Mobilization
Mon 6/11/07 Tue 6/12/07
Install Elevator Pads/Protection
Wed 6/13/07 Wed 6/13/07
Temporary Fire and Security System
Thu 6/28/07 Thu 7/5/07
Install Communications Riser
Tue 6/12/07 Mon 6/25/07
Install Misc. Electrical
Mon 6/25/07 Fri 7/6/07
Feasability of Existing Copper OSP
Mon 6/18/07 Tue 6/19/07
Install New Copper and Fiber OSP
Wed 6/20/07 Thu 7/12/07
Install New Copper OSP to MDF (Sub)
Wed 6/20/07 Mon 6/25/07
Install Protectors & Term OSP @ MDF
Wed 6/27/07 Mon 7/2/07
Splice OSP @ Man-hole
Mon 7/9/07 Tue 7/10/07
Test OSP - end to end (300 pr)
Wed 7/11/07 Thu 7/12/07
Install New Fiber OSP to MDF (Sub)
Wed 6/20/07 Mon 6/25/07
Install Fiber shelf & Term Fiber @ MDF
Fri 6/29/07 Tue 7/3/07
Fushion Splice Fiber @ Man-hole
Thu 7/5/07 Fri 7/6/07
Test Fiber - end to end
Mon 7/9/07 Mon 7/9/07
IDF's & MDF's
Mon 6/11/07 Wed 7/25/07
Abatement by SPU - Vertical
Mon 6/11/07 Thu 6/14/07
Coredrill - Vertical
Wed 6/13/07 Thu 6/28/07
Install & Paint New Plywood
Mon 6/18/07 Mon 6/25/07
Install 4" Sleeves & Conduits
Mon 6/18/07 Fri 6/29/07
Install New Light Fixtures / Outlets
Mon 6/25/07 Fri 6/29/07
Install Cable Tray & Equip. Racks - T4
Wed 6/27/07 Mon 7/9/07
Install Copper & Fiber Backbone
Wed 7/11/07 Wed 7/25/07
Install, Term & Test Copper BB - T4
Wed 7/11/07 Thu 7/19/07
Install, Term & Test Fiber BB
Fri 7/13/07 Fri 7/20/07
Firestopping
Tue 7/24/07 Wed 7/25/07
Install HVAC Units
Mon 7/2/07 Mon 7/9/07
Misc Roofing Repairs
Tue 7/10/07 Wed 7/11/07
SPU Punch/Accept IDF's, MDF's
Thu 7/12/07 Wed 7/18/07
CAT6 Horizontal Cable
Mon 6/11/07 Thu 9/6/07
Protect Misc Finishes
Mon 6/11/07 Mon 6/18/07
Abatement by SPU - Horizontal
Mon 6/11/07 Mon 6/18/07
Coredrill - Horizontal
Tue 6/12/07 Mon 7/9/07
Install SNMR all floors
Wed 6/13/07 Wed 8/8/07
Install CAT6 Horizontal Cable
Mon 6/25/07 Thu 8/30/07
Rough-in MDF to all IDF rooms
Mon 6/25/07 Fri 6/29/07
T1 = 4 techs
Mon 6/25/07 Fri 6/29/07
R/I CAT6 A1-3 left = Team 1
Tue 6/26/07 Fri 7/6/07
T3 = 3 techs
Tue 6/26/07 Fri 7/6/07
IDF-1 and MDF available to SPU
Mon 7/9/07 Mon 7/9/07
R/I CAT6 A1-3 right = Team 2
Tue 6/26/07 Fri 7/6/07
T4 = 2 techs
Tue 6/26/07 Fri 7/6/07
IDF-2 to SPU
Mon 7/9/07 Mon 7/9/07
R/I CAT6 A4-5-6 right = Team 1 (212)
Mon 7/16/07 Fri 7/27/07
IDF-3 to SPU
Mon 7/30/07 Mon 7/30/07
R/I CAT6 A4-5-6 left = Team 2 (223)
Mon 7/16/07 Fri 7/27/07
IDF-4 to SPU
Mon 7/30/07 Mon 7/30/07
Terminate CAT6 @ Desktop
Fri 7/6/07 Mon 8/6/07
Term CAT6 - A1-3 left = T3
Fri 7/6/07 Fri 7/13/07
Term CAT6 - A1-3 right = T3
Mon 7/9/07 Mon 7/16/07
Term CAT6 - A4-5-6 right = T3
Fri 7/27/07 Mon 8/6/07
Term CAT6 - A4-5-6 left = T3
Fri 7/27/07 Mon 8/6/07
Terminate CAT6 @ IDFs
Wed 8/1/07 Thu 8/30/07
Term CAT6 - A1-3 left = T4
Wed 8/1/07 Fri 8/3/07
IDF-1 available to SPU
Mon 8/6/07 Fri 8/10/07
Term CAT6 - A1-3 right = T4
Mon 8/6/07 Thu 8/9/07
IDF-2 to SPU
Fri 8/10/07 Thu 8/16/07
Term CAT6 - A4-5-6 right = T4
Fri 8/10/07 Thu 8/16/07
IDF-3 to SPU
Fri 8/17/07 Thu 8/23/07
Term CAT6 - A4-5-6 left = T4
Fri 8/17/07 Thu 8/23/07
IDF-4 to SPU
Fri 8/24/07 Thu 8/30/07
Test CAT6
Mon 8/6/07 Tue 8/28/07
Term CAT6 - A1-3 left = T1
Mon 8/6/07 Tue 8/7/07
Term CAT6 - A1-3 right = T1
Thu 8/9/07 Tue 8/14/07
Term CAT6 - A4-5-6 right = T1
Wed 8/15/07 Tue 8/21/07
Term CAT6 - A4-5-6 left = T1
Wed 8/22/07 Tue 8/28/07
CMU Patch & Repair
Mon 7/30/07 Wed 8/22/07
Firestopping
Mon 8/13/07 Fri 8/24/07
Furnish and Install Custom Built Boxes
Mon 6/25/07 Thu 7/19/07
GWB Related Scope
Mon 6/11/07 Thu 7/5/07
Concealed Spline Ceiling Repair/Replace
Mon 7/30/07 Wed 8/22/07
Misc. Painting
Mon 7/23/07 Wed 8/15/07
Construction Cleaning
Mon 7/30/07 Wed 8/22/07
Misc Flooring Patch & Repair
Mon 7/30/07 Wed 8/22/07
SPU staff - room and furniture re-conditioning
Thu 8/16/07 Thu 9/6/07
Boiler replacement
Mon 6/11/07 Tue 8/28/07
Boiler room abatement
Mon 6/11/07 Fri 6/15/07
Boiler room demolition and removal
Mon 6/18/07 Fri 6/29/07
Boiler installation
Mon 7/2/07 Mon 8/27/07
Boiler replacement completed
Tue 8/28/07 Tue 8/28/07
SPU punch and accept
Wed 8/29/07 Fri 8/31/07
Hill Hall
Mon 6/11/07 Wed 9/5/07
Mobilization
Mon 6/11/07 Tue 6/12/07
Install Elevator Pads/Protection
Wed 6/13/07 Wed 6/13/07
Temporary Fire and Security System
Mon 7/9/07 Fri 7/13/07
Install Communications Riser
Mon 6/11/07 Fri 7/6/07
Install Misc. Electrical
Mon 7/9/07 Fri 7/13/07
Install New Copper and Fiber OSP
Mon 7/2/07 Mon 7/23/07
Install New Copper OSP to MDF (Sub)
Mon 7/2/07 Tue 7/3/07
Install New Copper OSP to OUS (Sub)
Thu 7/5/07 Fri 7/6/07
Install Protectors & Term OSP @ MDF
Fri 7/6/07 Mon 7/9/07
Install Protectors & Term OSP @ OUS
Mon 7/9/07 Mon 7/9/07
Splice OSP @ Man-hole
Mon 7/16/07 Wed 7/18/07
Test OSP - end to end (400 pr)
Thu 7/19/07 Mon 7/23/07
Install New Fiber OSP to MDF (Sub)
Mon 7/2/07 Tue 7/3/07
Install New Fiber OSP to OUS (Sub)
Thu 7/5/07 Fri 7/6/07
Install New Fiber OSP to Hillford Hse (Sub)
Mon 7/9/07 Tue 7/10/07
Install Fiber shelf & Term Fiber @ MDF
Mon 7/9/07 Wed 7/11/07
Install F shelf & Term Fiber @ OUS
Thu 7/12/07 Thu 7/12/07
Install F shelf & Term Fiber @ Hillford Hse
Fri 7/13/07 Fri 7/13/07
Fushion Splice Fiber @ Man-hole
Mon 7/16/07 Wed 7/18/07
Test Fiber - end to end
Thu 7/19/07 Fri 7/20/07
IDF's & MDF's
Mon 6/11/07 Wed 7/25/07
Abatement by SPU - Vertical
Mon 6/11/07 Thu 6/14/07
Coredrill - Vertical
Wed 6/13/07 Tue 6/26/07
Install & Paint New Plywood
Mon 6/18/07 Mon 6/25/07
Install 4" Sleeves
Mon 6/18/07 Fri 6/29/07
Install New Light Fixtures / Outlets
Mon 6/25/07 Fri 6/29/07
Install Cable Tray & Equip. Racks - T4
Wed 6/27/07 Mon 7/9/07
Install Copper & Fiber Backbone
Wed 7/11/07 Wed 7/25/07
Install, Term & Test Copper BB - T4
Wed 7/11/07 Thu 7/19/07
Install, Term & Test Fiber BB
Fri 7/13/07 Fri 7/20/07
Firestopping
Tue 7/24/07 Wed 7/25/07
Install HVAC Units
Mon 7/2/07 Mon 7/9/07
Misc Roofing Repairs
Tue 7/10/07 Wed 7/11/07
SPU Punch/Accept IDF's, MDF's
Thu 7/12/07 Wed 7/18/07
CAT6 Horizontal Cable
Mon 6/11/07 Wed 8/22/07
Protect Misc Finishes
Mon 6/11/07 Mon 6/18/07
Abatement by SPU - Horizontal
Mon 6/11/07 Mon 6/18/07
Coredrill - Horizontal
Tue 6/12/07 Mon 7/2/07
Install SNMR all floors
Wed 6/13/07 Tue 7/17/07
Install CAT6 Horizontal Cable
Mon 6/25/07 Wed 8/22/07
Rough-in CAT6 H-1 = Team 1 (51)
Mon 6/25/07 Tue 6/26/07
T1 = 4 techs
Mon 6/25/07 Tue 6/26/07
Rough-in CAT6 H-2 = Team 2 (97)
Mon 6/25/07 Thu 6/28/07
T2 = 4 techs
Mon 6/25/07 Thu 6/28/07
Rough-in CAT6 H-3 = Team 1 (182)
Mon 7/2/07 Wed 7/11/07
T3 = 3 techs
Mon 7/2/07 Wed 7/11/07
Rough-in CAT6 H-4 = Team 2 (183)
Thu 7/5/07 Fri 7/13/07
T4 = 2 techs
Thu 7/5/07 Fri 7/13/07
Rough-in CAT6 H-5 = Team 1 (209)
Wed 7/18/07 Fri 7/27/07
IDF-1 and MDF available to SPU
Mon 7/30/07 Mon 7/30/07
Rough-in CAT6 H-6 = Team 2 (102)
Fri 7/20/07 Wed 7/25/07
IDF-2 available to SPU
Thu 7/26/07 Thu 7/26/07
Terminate CAT6 @ Desktop
Tue 6/26/07 Thu 8/2/07
Term CAT6 - H1 = T3
Tue 6/26/07 Wed 6/27/07
Term CAT6 - H2 = T3
Thu 6/28/07 Mon 7/2/07
Term CAT6 - H3 = T3
Wed 7/11/07 Mon 7/16/07
Term CAT6 - H4 = T3
Fri 7/13/07 Wed 7/18/07
Term CAT6 - H5 = T3
Fri 7/27/07 Thu 8/2/07
Term CAT6 - H6 = T3
Wed 7/25/07 Fri 7/27/07
Terminate CAT6 @ IDFs
Mon 7/23/07 Wed 8/22/07
Term CAT6 - H1 & H2 = T4
Mon 7/23/07 Wed 7/25/07
Term CAT6 - H3 & H4 = T4
Fri 7/27/07 Wed 8/1/07
Term CAT6 - H5 & H6 = T4
Thu 8/2/07 Wed 8/8/07
IDF-1 and 2 available to SPU
Thu 8/9/07 Wed 8/22/07
Test CAT6
Mon 7/30/07 Fri 8/17/07
Test CAT6 - H1 & H2 = T1(2 techs)
Mon 7/30/07 Tue 7/31/07
Test CAT6 - H3 & H4 = T1(2 techs)
Mon 8/6/07 Thu 8/9/07
Test CAT6 - H5 & H6 = T1(2 techs)
Tue 8/14/07 Fri 8/17/07
CMU Patch & Repair
Mon 7/30/07 Wed 8/22/07
Firestopping
Mon 8/13/07 Fri 8/24/07
Furnish and Install Custom Built Boxes
Mon 6/25/07 Thu 7/19/07
GWB Related Scope
Mon 7/16/07 Wed 8/8/07
Concealed Spline Ceiling Repair/Replace
Mon 7/23/07 Wed 8/15/07
Misc. Painting
Mon 7/30/07 Wed 8/22/07
Construction Cleaning
Mon 7/30/07 Wed 8/22/07
Misc Flooring Patch & Repair
Mon 7/30/07 Wed 8/22/07
Project Completion
Wed 8/1/07 Wed 9/5/07
Restore Security/Fire Alarm System
Wed 8/1/07 Thu 8/2/07
Final Inspections / Signoff Permits
Mon 8/20/07 Wed 8/22/07
SPU Punch and Accept
Wed 8/29/07 Fri 8/31/07


Art Center Renovation

Project Manager: Darrell Jacobsen, 206-281-2322, djacob@spu.edu
Construction Timeline: June 12, 2007 - August 30, 2007
Architect: Steve Beck Consulting
Contractor: Davis Schueller Inc.