|
|
|
| Capital Projects Status Reports | |
| Projects in Design
* Science Building Phase I * Stearns Building Renovation * Marston Hall Renovation * Miller Science Learning Center Renovation |
Projects in
Construction
* Emerson Residence Hall |
| Capital Renewal Projects | Completed Projects
* Gwinn Commons |
Project Manager: Dave Church,
281-2602, dchurch@spu.edu
Take a look at the initial schematic design
Project Manager: Dave Church,
281-2602, dchurch@spu.edu
Project Manager: Dave Church,
281-2602, dchurch@spu.edu
Project Manager: Darrell Hines,
281-2844 dhines@spu.edu
Take a look at the initial schematic design
Project Manager: Dave Church,
281-2602, dchurch@spu.edu
Take a virtual tour through the new dining facility.
Construction Timeline: July 3, 2001 to September 8, 2003
Architect: Miller Hull Architects
Contractor: To be Determined
for the new science facility.
Program Planning, Architect
Selection & Schematic Design
Solicit Architectural Proposals
Select Architect
B.O.T. Approval To Hire Architect
Program Verification &
Schematics
B.O.T. Approval To Continue (DD
& CD)
Design & Construction Doc's
Development
B.O.T. Approval For Marston &
MSLC Planning
Permit Application
Construction Bidding
B.O.T. Approval For Marston &
MSLC Projects
B.O.T. Final Approval For Science
Building Construction
Marston Renov. & Reloc. of
Green & Tiffany Occup.
Science Building Construction
Furnishings & Equipment
Installation
Phase I Ribbon Cutting
MSLC Renovation
Fund Raising Campaign
Science Building
Endowment
Annual fund
Renovation Timeline: June 18, 2001 to September 15, 2001
Architect: Miller Hull Architects
Contractor: To be Determined
Renovation Timeline: December 1, 2003 to June 30, 2004
Architect: Miller Hull Architects
Projects in Construction
Project Superintendent: Wayne Elling, 281-2599
elling@spu.edu
Construction Timeline: May 5, 2000 - June 22, 2001
Architect: Lorig Associates, L.L.C. and Mithun Partners
Contractor: W.G. Clark
for the revised Residence Hall.
Completed Projects
Construction Timeline: April 2, 1999 - September 13, 1999
Architect: LMN Architects
Contractor: McCarthy
Building Permit
Process
Alternative Feeding
Plan
Site selection
Contract with vendor
Temp Use permit
Barbecue Purchase
Stearns development -
Interior
Storage relocation
Relocate Landscape
Stearns Development -
Exterior
Kitchen Trailer
rental
Marriott Occupancy
Stearns operational
Stearns Restoration
Summer food service
at the SUB
Sign Contract with
SDL
Order furnishings
Asbestos Abatement
Phase I
Decide Gwinn AV
package
Purchase Subway cart
Gwinn Site move out
Salvage / Asbestos
Abatement Phase II
Construction
Floor 1 & 2
Occupancy
Marriott setup /
Training
Building
Commissioning
Floor 3 Occupancy
Fall Quarter Starts
Copyright © 2008 Seattle Pacific University.
General Information: (206) 281-2000