Capital Projects Status Reports

Projects in Design
* Science Building Phase I
* Stearns Building Renovation
* Marston Hall Renovation
* Miller Science Learning Center Renovation
Projects in Construction
* Emerson Residence Hall
Capital Renewal Projects Completed Projects
* Gwinn Commons

Note: If you don't have PowerPoint 97, then download the viewer from Microsoft.


Projects in Design

Science Building Phase I

Project Manager: Dave Church, 281-2602, dchurch@spu.edu
Construction Timeline: July 3, 2001 to September 8, 2003
Architect: Miller Hull Architects
Contractor: To be Determined

Take a look at the initial schematic design
for the new science facility.

Task Name Duration Start Finish
Program Planning, Architect Selection & Schematic Design 200 days Mon 5/18/98 Fri 2/19/99
Solicit Architectural Proposals 50 days Mon 5/18/98 Fri 7/24/98
Select Architect 10 days Mon 7/20/98 Fri 7/31/98
B.O.T. Approval To Hire Architect 1 day Thu 8/6/98 Thu 8/6/98
Program Verification & Schematics 141 days Fri 8/7/98 Fri 2/19/99
B.O.T. Approval To Continue (DD & CD) 1 day Fri 2/19/99 Fri 2/19/99
Design & Construction Doc's Development 289 days Mon 2/22/99 Thu 3/30/00
B.O.T. Approval For Marston & MSLC Planning 2 days Fri 5/21/99 Mon 5/24/99
Permit Application 110 days Mon 4/3/00 Fri 9/1/00
Construction Bidding 87 days Tue 10/3/00 Wed 1/31/01
B.O.T. Approval For Marston & MSLC Projects 1 day Fri 5/19/00 Fri 5/19/00
B.O.T. Final Approval For Science Building Construction 1 day Fri 2/16/01 Fri 2/16/01
Marston Renov. & Reloc. of Green & Tiffany Occup. 137 days Mon 6/11/01 Tue 12/18/01
Science Building Construction 525 days Tue 7/3/01 Mon 7/7/03
Furnishings & Equipment Installation 24 days Mon 7/7/03 Thu 8/7/03
Phase I Ribbon Cutting 1 day Mon 9/8/03 Mon 9/8/03
MSLC Renovation 181 days Mon 12/1/03 Mon 8/9/04
Fund Raising Campaign 1305 days Fri 2/19/99 Thu 2/19/04
Science Building 522 days Fri 2/19/99 Mon 2/19/01
Endowment 1305 days Fri 2/19/99 Thu 2/19/04
Annual fund 1305 days Fri 2/19/99 Thu 2/19/04


Marston Hall Renovation

Project Manager: Dave Church, 281-2602, dchurch@spu.edu
Renovation Timeline: June 18, 2001 to September 15, 2001
Architect: Miller Hull Architects
Contractor: To be Determined


MSLC Renovation

Project Manager: Dave Church, 281-2602, dchurch@spu.edu
Renovation Timeline: December 1, 2003 to June 30, 2004
Architect: Miller Hull Architects


Projects in Construction

Emerson Residence Hall

Project Manager: Darrell Hines, 281-2844 dhines@spu.edu
Project Superintendent: Wayne Elling, 281-2599 elling@spu.edu
Construction Timeline: May 5, 2000 - June 22, 2001
Architect: Lorig  Associates, L.L.C. and Mithun Partners
Contractor: W.G. Clark

Take a look at the initial schematic design
for the revised Residence Hall.


Completed Projects

Gwinn Commons Renovation

Project Manager: Dave Church, 281-2602, dchurch@spu.edu
Construction Timeline: April 2, 1999 - September 13, 1999
Architect: LMN Architects
Contractor: McCarthy

Take a virtual tour through the new dining facility.

Task Name Duration Start Finish
Building Permit Process 130 days Tue 9/8/98 Mon 3/8/99
Alternative Feeding Plan 265 days Mon 9/21/98 Fri 9/24/99
Site selection 55 days Mon 9/21/98 Fri 12/4/98
Contract with vendor 1 day Fri 12/4/98 Fri 12/4/98
Temp Use permit 45 days Mon 12/7/98 Fri 2/5/99
Barbecue Purchase 12 days Fri 1/15/99 Mon 2/1/99
Stearns development - Interior 40 days Mon 1/25/99 Fri 3/19/99
Storage relocation 5 days Mon 2/1/99 Fri 2/5/99
Relocate Landscape 5 days Mon 2/1/99 Fri 2/5/99
Stearns Development - Exterior 110 days Mon 2/8/99 Fri 7/9/99
Kitchen Trailer rental 86 days Mon 3/15/99 Mon 7/12/99
Marriott Occupancy 5 days Mon 3/22/99 Fri 3/26/99
Stearns operational 75 days Mon 3/29/99 Fri 7/9/99
Stearns Restoration 25 days Mon 7/12/99 Fri 8/13/99
Summer food service at the SUB 55 days Mon 7/12/99 Fri 9/24/99
Sign Contract with SDL 1 day Mon 11/23/98 Mon 11/23/98
Order furnishings 1 day Mon 11/23/98 Mon 11/23/98
Asbestos Abatement Phase I 16 days Fri 12/4/98 Fri 12/25/98
Decide Gwinn AV package 65 days Mon 12/7/98 Fri 3/5/99
Purchase Subway cart 19 days Fri 1/15/99 Wed 2/10/99
Gwinn Site move out 15 days Mon 3/15/99 Fri 4/2/99
Salvage / Asbestos Abatement Phase II 10 days Mon 3/15/99 Fri 3/26/99
Construction 125 days Mon 4/5/99 Fri 9/24/99
Floor 1 & 2 Occupancy 1 day Mon 8/16/99 Mon 8/16/99
Marriott setup / Training 20 days Tue 8/17/99 Mon 9/13/99
Building Commissioning 29 days Tue 8/17/99 Fri 9/24/99
Floor 3 Occupancy 1 day Fri 9/24/99 Fri 9/24/99
Fall Quarter Starts 1 day Mon 9/27/99 Mon 9/27/99